This project involved the construction of foundations for crude oil and fuel oil tanks, including protective walls, retaining structures, and various infrastructure works such as drainage lines, fire water lines, and oily water drainage lines. The project included concrete road and site surfacing, steel barriers, and fencing, along with concrete foundations for pipe bridges and cathodic protection.
Key Project Activities:
Retaining Wall, Gabion, and Anchoring Works:
Gabion Wall: 2,100 m² manufactured
Fore Piling: 9,605 m manufactured
Soil Anchoring: 16,100 m manufactured
Barbican Construction: 975 m manufactured
Reinforced Concrete Manufacturing: 2,000 m³
Reinforcement Manufacturing: 1,600 tons
Slope Stabilization Works:
Excavation: 30,000 m³
Filling: 43,000 m³
Geogrid Manufacturing: 1,845 m²
Fore Piling: 7,300 m manufactured
Reinforced Concrete Manufacturing: 1,000 m³
Shotcrete Works: 2,600 m²
Instrumentation:
Inclinometer: 150 m manufactured
Extensometer: 100 m manufactured
Piezometer: 135 m manufactured
Load Cell Manufacturing: 8 units
Structural Steel Manufacturing: 1,400 tons
Concrete Paving (Area): 66,000 m²
Reinforced Concrete Manufacturing: 23,000 m²
Excavation and Granular Filling: 1,000,000 m³ excavation and 140,000 m³ granular filling
Construction and Mechanical Works:
This project aims to enhance the refinery's storage capacity and operational flexibility. The infrastructure works portion was completed in May 2020 and handed over for superstructure works.
Specific Activities:
Excavation: 100,000 m³
Filling: 90,000 m³
Reinforced Fore Piling: 18,000 m manufactured
Concrete Road Construction: 2,100 m
Operating Lines (Piping) Installation: 63,000 WDI
Electrical and Instrumentation Works:
This project involves the installation of all energy lines for equipment related to SOCAR A.Ş.’s crude oil and fuel storage tanks in the Aliağa peninsula. It includes the mounting of all measurement instruments for tanks and pipelines, protective systems such as grounding, lightning protection, fire detection systems, and site lighting, camera, and communication systems. The project will conclude with the testing and commissioning of all systems, finalized by loading products into the tanks.
Additional Works:
The installation of 10 mixer motors and the corresponding mixers for SOCAR A.Ş.'s crude oil and fuel tanks is also included in the scope of work.
Project Details
Fuel Pump and Auxiliary Systems Installation
Equipment: Installation of 6 product/raw material pumps and associated pump motors and accessories.
Systems Installed:
Instrument air system
Raw water lines
Utility lines
Plant air system
Fire water system
Foam system
Air cooler system
Electrical Works:
Installation of switchgear, MCC, field panels (MOV, ESD, FSD, SLP, NLP, etc.), MCS, RIB, TECP, SECP panels, and all field JB installations.
Cathodic protection for underground steel pipes.
Installation of 256,000 meters of high voltage (OG), low voltage (AG), and signal cables.
Calibration and installation of fire, gas, telephone, CCTV systems, and tank measurement instruments (level, temperature, etc.), along with field instruments (PT, FT, LT, TT, CT, PG, TE, MOV, PSV, check valve, gate valve, etc.).
Lighting: Installation of all road and field lighting.
Grounding System: Establishment and integration into the main facility loop.
Testing and Commissioning Activities: Including motor run tests, calibration tests, cable hi-pot tests, 1/0 checks, pipe flushing, and hydrostatic tests.
Documentation: Preparation of test and quality documents (ITP, MS, FQD, etc.).
 
         
                         
                                         
                                         
                                     
                        



